The Chander Kunj demolition contract for two unsafe towers at the Army Welfare Housing Organisation’s (AWHO) complex in Vyttila, Kochi, was signed on Saturday, November 21, Onmanorama reported on Wednesday, November 25. Mumbai-based Edifice Engineering will bring down Towers B and C on Silver Sand Island by controlled implosion, possibly by mid-April 2027, though no blast date has been fixed.
Fort Kochi Revenue Divisional Officer G Sai Krishna signed for the High Court-appointed executive committee headed by the Ernakulam District Collector, and project manager Shaji Koshy signed for Edifice, the report said. The firm carried out the Maradu apartment demolitions, The South First reported.
Chander Kunj demolition contract sets a six-month schedule
The contract allows 24 weeks for the main work, plus 15 days each for mobilisation and demobilisation. Engineering plans are due by December 21, and the implosion is planned for the 16th week. Debris removal and clearing of the site down to the pile caps should be finished by week 24. The blast date must be communicated to authorities two weeks in advance, and the clock starts only after every apartment has been handed over.
The net contract value is ₹9,66,40,689, excluding GST, after an estimated scrap value of ₹6,25,15,000 is deducted, according to Onmanorama. Edifice must furnish a ₹1 crore performance bank guarantee and take out commercial general liability insurance of at least ₹75 crore within a month. It will be paid 25% as a mobilisation advance, 25% two weeks after the implosion subject to PWD certification, and the remaining 50% after debris disposal and site handover.
AWHO had already deposited ₹9.60 crore, excluding GST, in an escrow account, The South First reported on November 20. It put the total cost of the demolition at about ₹15 crore, including more than ₹5 crore expected from recoverable materials.
Tower A families and the Kochi Metro line must be protected
Fifty-six families still live in the adjoining Tower A. The contract requires 12-foot steel barricades and hessian cloth around that tower, temporary parking for its residents, the shifting of the sewage treatment plant, transformers and other utilities, two misting systems to control dust and a full-time safety officer, Onmanorama said. IIT Madras will check Tower A’s structural safety before and after the blast.
The Kochi Metro viaduct runs about 100 to 125 feet from Tower C, and clearances are needed from PESO, KSEB, Kochi Metro Rail Ltd, the police and the fire service. “Our first priority is the habitability of Tower A,” an Edifice official told Onmanorama.
How the Vyttila towers came to be condemned
AWHO built the complex in 2018, and it later developed serious structural problems. The two towers were evacuated after assessments found severe deterioration and a risk of collapse, according to The South First. The Kerala High Court ordered demolition and reconstruction on February 3, 2025, and the Collector’s executive committee was formed on February 12 that year.
Edifice was selected on June 1, 2026. A rival bidder challenged the choice, but the High Court upheld it, and The South First said the court dismissed the petitions on November 9.
The two towers hold 208 condemned flats, largely owned by serving and retired Army personnel and their relatives. Owners began handing over keys to AWHO on November 20, and Edifice sources told Onmanorama that about 80% had done so. “We are waiting for all the flats to be handed over,” an Edifice official said.
What owners should know
Only some owners attended the first handover because of short notice, and another date is to be set to complete the process, The South First reported. Owners who have not yet handed over keys should watch for that date, since work cannot begin until every flat is with AWHO. No progress has been made on rebuilding, and a project management consultant has not yet been appointed, the outlet said.