A green and white E5 series Shinkansen high-speed train in Japan
An E5 series Shinkansen train in Japan. India’s Mumbai-Ahmedabad corridor is based on Japan’s Shinkansen system. Photo: MaedaAkihiko/Wikimedia Commons, CC BY-SA 4.0.

Trials of India’s first bullet train on the Mumbai-Ahmedabad high-speed rail corridor are expected to begin by the middle of 2027, with the first passenger service planned for the last quarter of that year on the Surat-Vapi stretch, Railway Minister Ashwini Vaishnaw has said, according to ANI.

The indigenous B28 trainset, designed for a top speed of 280 km per hour, is being built by the Integral Coach Factory in Chennai and Bharat Earth Movers Ltd (BEML). The rest of the corridor, up to Mumbai, will open in phases after the first section.

Vaishnaw had said in September that trial runs could start in May or June 2027, and that commercial operations would follow two to four months after testing, Millennium Post reported.

The project so far

The 508-km corridor will link Mumbai and Ahmedabad through 12 stations, including Thane, Virar, Vapi, Bilimora, Surat, Bharuch, Vadodara and Anand. It is being built by the National High Speed Rail Corporation Ltd (NHSRCL) with Japanese loans and technology from Japan’s Shinkansen network. The line is designed for speeds of up to 320 km per hour, and the full journey is expected to take a little under two hours, against eight to nine hours by road.

Work has moved faster in Gujarat than in Maharashtra, where land acquisition held up construction for years. The Maharashtra stretch includes a 21-km tunnel, about 7 km of it under the sea at Thane Creek, and an underground terminal at the Bandra-Kurla Complex in Mumbai.

The project has missed several deadlines since Prime Minister Narendra Modi and then Japanese Prime Minister Shinzo Abe laid the foundation stone in Ahmedabad in September 2017. In January 2026, Vaishnaw said the first bullet train was likely to run on August 15, 2027, starting with the Surat-Bilimora section, according to All India Radio.

Japan is financing most of the project through a low-interest loan from the Japan International Cooperation Agency (JICA), repayable over 50 years. The cost of the corridor has risen well above early estimates because of the delays.

What trials will test

Trials will check the track, signaling, power supply and trains working together. Passenger services can begin only after safety certification. Because the first section runs through south Gujarat, commuters between Surat, Bilimora and Vapi are likely to be the first to ride, well before the line reaches Mumbai.

The choice of an Indian-built trainset for the first runs is significant. The original plan relied on Japanese Shinkansen trains, and building trains at home is meant to cut costs and help Indian manufacturers win a share of future high-speed projects.

Why Kerala is watching

Kerala has debated its own SilverLine semi-high-speed rail project for years, with arguments over cost, land and the environment. The Mumbai-Ahmedabad corridor is the country’s first full-scale high-speed line, and how it performs once trains start running is likely to shape future decisions on fast rail in other states.

For now, the next milestone is the start of track trials. A further slip in that date would push back the opening of a project that has already taken more than nine years.

Chooduvartha Desk

By Chooduvartha Desk

The Chooduvartha Desk reports news for Malayalis in Kerala, the Gulf and around the world. Our editorial standards explain how reports are prepared and verified. To report an error, write to chooduvartha@gmail.com.